Scope of Work
P&R Tower Company completed a 4-tower diplex installation for two 50kW AM broadcast stations at a site in Hayward, CA, serving New Inspiration (Salem Communications). Each tower was fully assembled on the ground — including tower lights, high-capacity insulators, and the top-loading skirt — and bonded prior to installation.
Site Challenges & Safety
Because of the soft roof and California structural installation safety requirements, the towers could not be assembled in place. The fully assembled and bonded towers were lifted and installed as complete units. The installation went flawlessly, with all structural and safety requirements met.
Equipment & Specifications
- Installation Type: 4-Tower Diplex Array
- Stations Served: 2 × 50kW AM Broadcast Stations
- Client: New Inspiration (Salem Communications)
- Pre-Assembly: Full tower assembly on the ground, including lights, high-capacity insulators, and top-loading skirt
- Bonding: Complete tower bonding completed on the ground prior to installation